The utility model discloses a descaling system with pneumatic control injection valve, manual valve, including the first water filling pipe, pre filling water valve, throttling device second, a water filling pipe, injection valve and manual valve, the first connecting flange; a water filling pipe, pre filling water valve, throttling device, water filling pipe and second injection valve are sequentially connected to form pre filled pipes; manual valve, flange and injection valve connected jet pipe; throttling device is provided with a plurality of spaced eccentric orifice plate throttling device is perpendicular to the central axis, the axis eccentric eccentric orifice axis and an adjacent eccentric eccentric orifice on the through hole the hole was staggered. The utility model except by gas injection valve control group used in the pre filling pipe of the descaling system, eccentric orifice plate throttling device in staggered throttling of high pressure water system, ensure smooth operation, pipeline without obvious impact vibration, but also to ensure the injection valve opening and closing smoothly, which makes the system stable pressure, pressure drop small.
【技術(shù)實(shí)現(xiàn)步驟摘要】
除鱗系統(tǒng)用氣控噴射閥組
本技術(shù)涉及高壓閥門(mén)領(lǐng)域,具體地指一種除鱗系統(tǒng)用氣控噴射閥組。
技術(shù)介紹
在工業(yè)鍛造、擠壓系統(tǒng)、鋼廠等高壓工業(yè)水系統(tǒng)中,噴射閥組件安裝在除鱗系統(tǒng)的終端,對(duì)除鱗過(guò)程中的高壓水的噴射進(jìn)行控制,起到除去鋼板或鋼坯表面氧化皮的作用。在正常工況條件下,噴射閥處于關(guān)閉狀態(tài),高壓水經(jīng)過(guò)手動(dòng)閘閥和預(yù)充水閥給高壓水系統(tǒng)(即噴射閥的出口)補(bǔ)水。當(dāng)除鱗系統(tǒng)進(jìn)入預(yù)定工位,控制系統(tǒng)得到除鱗信號(hào),噴射閥氣控裝置得電換向,噴射閥打開(kāi)。此時(shí),高壓預(yù)充水系統(tǒng)預(yù)充水閥關(guān)閉,除鱗系統(tǒng)開(kāi)始噴射高壓水除鱗。當(dāng)除鱗系統(tǒng)離開(kāi)預(yù)定工位,控制系統(tǒng)得到結(jié)束除鱗信號(hào),噴射閥氣控裝置失電換向,噴射閥關(guān)閉。同時(shí),高壓預(yù)充水系統(tǒng)預(yù)充水閥打開(kāi),開(kāi)始給高壓水系統(tǒng)補(bǔ)水。此時(shí),除鱗系統(tǒng)噴射除鱗結(jié)束。除鱗過(guò)程中,氣控噴射高壓水的過(guò)程屬于高壓、高危害工序,氣控噴射閥組件中的噴射閥啟閉頻繁,會(huì)對(duì)系統(tǒng)管路造成的較大的沖擊和震動(dòng),因此存在較大的安全隱患。當(dāng)管路中的噴射閥突然關(guān)閉或者開(kāi)啟時(shí),管路中液體介質(zhì)的壓力發(fā)生急劇交替升降的阻尼波動(dòng)過(guò)程,產(chǎn)生液壓沖擊(水錘)現(xiàn)象,會(huì)造成除鱗系統(tǒng)無(wú)法正常工作、生產(chǎn)中斷,嚴(yán)重的情況下甚至?xí)斐扇藛T傷亡。
技術(shù)實(shí)現(xiàn)思路
本技術(shù)的目的在于,提供一種的除鱗系統(tǒng)用氣控噴射閥組,能保證在除鱗過(guò)程中除鱗系統(tǒng)中的高壓水運(yùn)行平穩(wěn)、系統(tǒng)管路無(wú)明顯沖擊振動(dòng)。為實(shí)現(xiàn)上述目的,本技術(shù)所設(shè)計(jì)的除鱗系統(tǒng)用氣控噴射閥組包括手動(dòng)閘閥、第一充水管、預(yù)充水閥、節(jié)流降壓裝置、第二充水管、噴射閥及連接法蘭;所述手動(dòng)閘閥、所述第一充水管、所述預(yù)充水閥、所述節(jié)流降壓裝置、所述第二充水管及所述噴射閥順次連接形成預(yù)充水管路;所述手 ...
【技術(shù)保護(hù)點(diǎn)】
一種除鱗系統(tǒng)用氣控噴射閥組,其特征在于:所述除鱗系統(tǒng)用氣控噴射閥組包括手動(dòng)閘閥(1)、第一充水管(2)、預(yù)充水閥(3)、節(jié)流降壓裝置(4)、第二充水管(5)、噴射閥(6)及連接法蘭(7);所述手動(dòng)閘閥(1)、所述第一充水管(2)、所述預(yù)充水閥(3)、所述節(jié)流降壓裝置(4)、所述第二充水管(5)及所述噴射閥(6)順次連接形成預(yù)充水管路;所述手動(dòng)閘閥(1)、所述連接法蘭(7)及所述噴射閥(6)順次連接形成噴射管路;所述節(jié)流降壓裝置(4)內(nèi)沿所述預(yù)充水管路方向間隔設(shè)置有多個(gè)垂直于所述節(jié)流降壓裝置(4)中心軸線的偏心孔板(4.1),一個(gè)所述偏心孔板(4.1)上的偏心通孔(4.11)的軸線與相鄰的所述偏心孔板(4.1)上的所述偏心通孔(4.11)的軸線呈錯(cuò)開(kāi)設(shè)置。
【技術(shù)特征摘要】
1.一種除鱗系統(tǒng)用氣控噴射閥組,其特征在于:所述除鱗系統(tǒng)用氣控噴射閥組包括手動(dòng)閘閥(1)、第一充水管(2)、預(yù)充水閥(3)、節(jié)流降壓裝置(4)、第二充水管(5)、噴射閥(6)及連接法蘭(7);所述手動(dòng)閘閥(1)、所述第一充水管(2)、所述預(yù)充水閥(3)、所述節(jié)流降壓裝置(4)、所述第二充水管(5)及所述噴射閥(6)順次連接形成預(yù)充水管路;所述手動(dòng)閘閥(1)、所述連接法蘭(7)及所述噴射閥(6)順次連接形成噴射管路;所述節(jié)流降壓裝置(4)內(nèi)沿所述預(yù)充水管路方向間隔設(shè)置有多個(gè)垂直于所述節(jié)流降壓裝置(4)中心軸線的偏心孔板(4.1),一個(gè)所述偏心孔板(4.1)上的偏心通孔(4.11)的軸線與相鄰的所述偏心孔板(4.1)上的所述偏心通孔(4.11)的軸線呈錯(cuò)開(kāi)設(shè)置。2.根據(jù)權(quán)利要求1所述的除鱗系統(tǒng)用氣控噴射閥組,其特征在于:所述節(jié)流降壓裝置(4)還包括進(jìn)口法蘭(4.2)、多個(gè)順次連接的節(jié)流管(4.3)和出口法蘭(4.4),所述進(jìn)口法蘭(4.2)與所述預(yù)充水閥(3)的出口端相連,所述出口法蘭(4.4)與所述第二充水管(5)的入口端連接,兩端的所述節(jié)流管(4.3)分別與所述進(jìn)口法蘭(4.2)和所述出口法蘭(4.4)連接,所述進(jìn)口法蘭(4.2)的端面與所述節(jié)流管(4.3)的端面之間、每一所述節(jié)流管(4.3)中部、相鄰的所述節(jié)流管(4.3)的端面之間、所述節(jié)流管(4.3...
【專利技術(shù)屬性】
技術(shù)研發(fā)人員:陶力,李本林,張素珍,
申請(qǐng)(專利權(quán))人:湖北高中壓閥門(mén)有限責(zé)任公司,
類型:新型
國(guó)別省市:湖北,42